We are parties in a variety of legal actions that routinely arise out of the normal course of business, including legal actions seeking to establish liability directly through insurance contracts or indirectly through reinsurance contracts issued by Berkshire subsidiaries. Plaintiffs occasionally seek punitive or exemplary damages. We do not currently believe that such normal and routine litigation will have a material effect on our financial condition or results of operations. Information concerning certain legal matters involving certain of our subsidiaries follows.

Wildfires

PacifiCorp, a wholly-owned subsidiary of Berkshire Hathaway Energy Company (“BHE”), operates as a regulated electric utility in Utah, Oregon, Wyoming and other Western states. PacifiCorp is party to a variety of legal actions arising from wildfires that occurred in 2020 and 2022. Such actions are described below.

2020 Wildfires and 2022 McKinney Fire

The 2020 Wildfires occurred in September 2020, when a severe weather event with high winds contributed to several major wildfires, resulting in real and personal property and natural resource damage, personal injuries and loss of life and widespread power outages in Oregon and Northern California. The wildfires spread across certain parts of PacifiCorp’s service territory and surrounding areas across multiple counties in Oregon and California, burning over 500,000 acres in aggregate and included the Santiam Canyon, Beachie Creek, South Obenchain, Echo Mountain Complex, 242, Archie Creek, Slater and other fires. The Slater fire occurred in both Oregon and California. Third-party reports for these wildfires indicate over 2,000 structures were destroyed, including residences; several structures damaged; multiple individuals injured; and several fatalities.

Both the U.S. Department of Agriculture Forest Service (“USFS”) and the Oregon Department of Forestry (“ODF”) completed investigation reports related to a wildland fire that was first reported outside the Santiam Canyon on August 16, 2020 (“Beachie Creek Fire”), approximately three weeks before the severe weather event described above. ODF’s report concluded that embers from the pre-existing Beachie Creek Fire caused 12 fires within the Santiam Canyon. ODF’s report also found that PacifiCorp’s power lines did not contribute to the overall spread of fire into the Santiam Canyon even though PacifiCorp’s power lines ignited seven spot fires within the Santiam Canyon that were each suppressed.

The Beachie Creek Fire that spread into the Santiam Canyon burned approximately 193,000 acres; the South Obenchain fire burned approximately 33,000 acres; the Echo Mountain Complex fire burned approximately 3,000 acres; and the 242 fire burned approximately 14,000 acres. The James cases described below are associated with the Beachie Creek (Santiam Canyon), South Obenchain, Echo Mountain Complex and 242 fires, which are four distinct fires located hundreds of miles apart.

The 2022 McKinney Fire occurred on July 29, 2022, when a wildfire began in Siskiyou County, California within PacifiCorp’s service territory, burning over 60,000 acres. Third-party reports indicate that the 2022 McKinney Fire resulted in 11 structures damaged; 185 structures destroyed, including residences; 12 injuries; and four fatalities.

Notes to Consolidated Financial Statements

Note 22. Contingencies and commitments

Complaints and Demands Associated with the Wildfires

A significant number of complaints and demands alleging similar claims related to the Wildfires have been filed in Oregon and California, including a class action complaint in Oregon associated with the 2020 Wildfires (the “James” case) for which certain jury verdicts were issued as described below. The plaintiffs seek damages for economic losses, noneconomic losses, including mental suffering, emotional distress, personal injury and loss of life, punitive damages, other damages and attorneys’ fees. Several insurance carriers also filed subrogation complaints in Oregon and California with similar allegations. Additionally, PacifiCorp received correspondence from the U.S. and Oregon Departments of Justice regarding the potential recovery of certain costs and damages alleged to have occurred on federal and state lands in connection with certain of the 2020 Wildfires. As described below, substantially all outstanding complaints and demands are associated with the 2020 Wildfires, specifically the James case and the state of Oregon demands.

Substantially all amounts sought in outstanding complaints and demands filed in Oregon are associated with the James mass complaints described below, as well as stayed cases for which motions have been filed for consolidation into the James case and state of Oregon demands. Oregon law provides for the doubling of economic and property damages in the event the defendant is found to have acted with gross negligence, recklessness, willfulness or malice. Oregon law provides for trebling of damages associated with timber, shrubs and produce in the event the defendant is determined to have willfully and intentionally trespassed. For class actions, amounts specified by the plaintiffs in the complaints include amounts based on estimates of the potential class size, which ultimately may be significantly greater than estimated.

PacifiCorp has settled various claims associated with the 2020 and 2022 Wildfires, including all wrongful death claims and federal government demands and complaints. For the Archie Creek fire, Slater fire and 2022 McKinney Fire, settlements have been reached with substantially all plaintiffs. For the Santiam Canyon, Echo Mountain Complex, South Obenchain and 242 fires, while PacifiCorp settled claims with individual plaintiffs who were granted substitution of counsel in the James case, claims remain outstanding for a substantial number of plaintiffs associated with the James case. In addition, claims were settled with the Oregon wineries and with the federal government. PacifiCorp is also actively cooperating with the Oregon Department of Justice on resolving its alleged claims. Refer below for information regarding the Oregon Court of Appeals opinion issued in April 2026 pertaining to the James class action complaint.

The James Case

On September 30, 2020, a class action complaint against PacifiCorp captioned Jeanyne James et al. v. PacifiCorp, (“James”) was filed in Oregon Circuit Court in Multnomah County, Oregon (“Multnomah County Circuit Court Oregon”). The complaint was filed by Oregon residents and businesses who sought to represent a class of all Oregon citizens and entities whose real or personal property was harmed beginning on September 7, 2020, by wildfires in Oregon allegedly caused by PacifiCorp. In November 2021, the plaintiffs filed an amended complaint to limit the class to include Oregon citizens allegedly impacted by the Santiam Canyon, Echo Mountain Complex, South Obenchain and 242 fires, as well as to add claims for noneconomic damages. The amended complaint alleged that PacifiCorp’s assets contributed to the Oregon wildfires occurring on or after September 7, 2020, and that PacifiCorp acted with gross negligence, among other things. The amended complaint seeks damages similar to those described above, including not less than $600 million of economic damages and in excess of $1 billion of noneconomic damages for the plaintiffs and the class.

Since the filing of the original class action complaint, several cases have been stayed pending consolidation into James and numerous James class members have been named and damages specified in various complaints. From April 2024 through January 2026, 1,760 James class members filed nine mass damages complaints in Multnomah County Circuit Court Oregon premised on the Phase I liability verdict, as described below, each referencing the original James case as the lead case. The James mass complaints make damages-only allegations seeking for each individual class member $5 million of economic damages, $25 million of noneconomic damages and punitive damages equal to 0.25 times the amount of economic and noneconomic damages, as well as doubling of economic damages. Complaints for some of the plaintiffs in the mass complaints have been dismissed, amended or re-filed.

The Multnomah County Circuit Court Oregon determined that the James case would be divided into a liability phase (“Phase I”) and a damages phase (“Phase II”). In June 2023, a jury in the Phase I liability trial found PacifiCorp’s conduct grossly negligent, reckless and willful as to each of the 17 named plaintiffs and the entire class. The jury awarded economic and noneconomic damages, as well as punitive damages. After the jury verdict, the Multnomah County Circuit Court Oregon doubled the Phase I plaintiffs’ economic damages, in accordance with Oregon law, and added punitive damages by applying a 0.25 multiplier to the awarded economic and noneconomic damages. The Multnomah County Circuit Court Oregon granted PacifiCorp’s subsequent motion to offset the damage awards by deducting insurance proceeds received by any of the plaintiffs.

Notes to Consolidated Financial Statements

Note 22. Contingencies and commitments

PacifiCorp subsequently appealed the Phase I liability verdict, and on April 8, 2026, the verdict was reversed and remanded by the Oregon Court of Appeals, as described in more detail below.

While PacifiCorp’s appeal of the Phase I verdict was pending, the Multnomah County Circuit Court Oregon held numerous Phase II trials in which a series of juries awarded damages to groups of James class members. The majority of these trials were scheduled pursuant to a case management order called “CMO No. 11.” PacifiCorp has filed notices of appeal for the subsequent jury verdicts in the Phase II trials once limited judgments are entered and any post-trial motions filed. The James jury verdicts to date have awarded total net damages of approximately $1.25 billion to 201 plaintiffs, including $133 million of doubled economic damages, $910 million of noneconomic damages, $244 million of punitive damages and partially reduced by estimated insurance offsets. To date, PacifiCorp has been required to bond the amounts awarded by the James limited judgments in order to stay payment of damages while on appeal. As of the date of this filing, PacifiCorp has posted bonds totaling $719 million associated with the limited judgments entered to date for 129 plaintiffs. Based on the April 2026 Oregon Court of Appeals opinion, the existing bonds could eventually be discharged and any future bonding requirements eliminated.

The Oregon Court of Appeals’ April 2026 opinion reversing the Phase I verdict explained that the Multnomah County Circuit Court Oregon erred in instructing the jury that they could “assume that the evidence at the trial applies to all class members.” The Oregon Court of Appeals further concluded that the erroneous jury instruction “was prejudicial to PacifiCorp” because it “gave rise to some likelihood that the jury reached an erroneous result.” Because the Oregon Court of Appeals reversed and remanded on the instructional error issue presented in PacifiCorp’s appellate brief, it did not address the majority of PacifiCorp’s other appealed issues. However, the Oregon Court of Appeals emphasized that the Multnomah County Circuit Court Oregon has the authority on remand to reconsider its class certification decision and reconsider whether a single class is appropriate in this case. The Oregon Court of Appeals determined PacifiCorp was the prevailing party and awarded costs to PacifiCorp. Either party can file a petition for review with the Oregon Supreme Court within 35 days of the Oregon Court of Appeals opinion, subject to extension. Whether the Oregon Supreme Court accepts a request for review is at its discretion.

On April 9, 2026, the Multnomah County Circuit Court Oregon ordered a stay of scheduled James Phase II trials (except for a trial that began April 6, 2026, and subsequently concluded on April 13, 2026) and mandatory mediation. The Multnomah County Circuit Court Oregon asked the parties to submit briefing on the merits, scope and duration of the stay in advance of a May 22, 2026, hearing.

Estimated Losses for and Settlements Associated with the Wildfires

A provision for a loss contingency is recorded when it is probable a liability is likely to occur and the amount of loss can be reasonably estimated. PacifiCorp evaluates the related range of reasonably estimated losses and records a loss based on its best estimate within that range or the lower end of the range if there is no better estimate.

Based on the facts and circumstances available to PacifiCorp as of the date of this filing, including (i) cause and origin investigations; (ii) ongoing settlement and mediation activities; (iii) other litigation matters and upcoming legal proceedings; and (iv) the status of the James case, PacifiCorp recorded cumulative estimated probable losses associated with the Wildfires of approximately $2.9 billion through March 31, 2026. PacifiCorp’s cumulative accrual includes estimates of probable losses for fire suppression costs, real and personal property damages, natural resource damages and noneconomic damages such as personal injury damages and loss of life damages that it is reasonably able to estimate at this time and which is subject to change as additional relevant information becomes available.

To date through March 31, 2026, PacifiCorp paid approximately $2.3 billion in settlements associated with the Wildfires, including $584 million in the first quarter of 2026. As a result of the settlements, various trials have been cancelled. PacifiCorp’s estimated unpaid liabilities in connection with the Wildfires were $577 million at March 31, 2026 and approximately $1.2 billion at December 31, 2025.

As of March 31, 2025, PacifiCorp had received all expected insurance recoveries. No additional insurance recoveries beyond those received to date are expected to be available.

It is reasonably possible PacifiCorp will incur material additional losses beyond the amounts accrued for the Wildfires that could have a material adverse effect on PacifiCorp’s financial condition. PacifiCorp is currently unable to reasonably estimate a specific range of possible additional losses that could be incurred due to the number of properties and parties involved, including claimants in the class to the James case, the variation in the types of properties and damages and the ultimate outcome of legal actions, including mediation, settlement negotiations, jury verdicts and the James appeals process, including the April 2026 Oregon Court of Appeals opinion.

Notes to Consolidated Financial Statements

Note 22. Contingencies and commitments

HomeServices of America, Inc.

HomeServices of America, Inc. (“HomeServices”) is also a wholly-owned subsidiary of BHE. HomeServices is currently defending against several antitrust cases, all in federal district courts. In each case, plaintiffs claim HomeServices and certain of its subsidiaries (and in one case, BHE) conspired with co-defendants to artificially inflate real estate commissions by following and enforcing multiple listing service (“MLS”) rules that require listing agents to offer a commission split to cooperating agents in order for the property to appear on the MLS (“Cooperative Compensation Rule”). None of the complaints specify damages sought. However, two cases also allege Texas state law deceptive trade practices claims, for which plaintiffs have asserted damages totaling approximately $9 billion by separate written notice as required by Texas law.

In one of these cases, Burnett (formerly Sitzer) et al. v. HomeServices of America, Inc. et al. (the “Burnett case”), a jury trial in the U.S. District Court for the Western District of Missouri (“U.S. District Court”) returned a verdict for the plaintiffs on October 31, 2023, finding that the named defendants participated in a conspiracy to follow and enforce the Cooperative Compensation Rule, which conspiracy had the purpose or effect of raising, inflating, or stabilizing broker commission rates paid by home sellers. The jury further found that the class plaintiffs had proved damages of $1.8 billion. Joint and several liability applies for the co-defendants. Federal law authorizes trebling of damages and the award of pre-judgment interest and attorney fees. To date, all defendants have reached settlements with the plaintiffs. All settlements received U.S. District Court approval, had final judgments entered by the court and were appealed to the U.S. Court of Appeals for the Eighth Circuit. All appeals were fully briefed by December 19, 2025, and oral arguments took place on January 14, 2026. A ruling from the court on the appeals is pending.

The final HomeServices settlement agreement reached with the plaintiffs on April 25, 2024 settles all claims asserted against HomeServices and certain of its subsidiaries in the Burnett case and effectuates a nationwide class settlement. The final settlement agreement includes scheduled payments totaling $250 million to be paid over four years. HomeServices has made payments in escrow of $130 million to date. If the settlement is not affirmed by the U.S. Court of Appeals for the Eighth Circuit, HomeServices intends to vigorously appeal on multiple grounds the jury’s findings and damage award in the Burnett case, including whether the case can proceed as a class action. The appeals process and further actions could take several years.

Other legal matters

In September 2024, National Indemnity Company (“NICO”) entered into a settlement agreement concerning certain non-insurance affiliates that filed voluntary petitions under Chapter 11 of the bankruptcy code in the United States Bankruptcy Court for the District of New Jersey (the “Court”) in 2023. Under the terms of the settlement agreement, NICO agreed to pay $535 million to the bankruptcy estate in consideration of a release of all estate causes of action against NICO and its affiliates. The Court’s approval of the settlement agreement over the objections of certain creditors is pending.

NICO and its affiliates also entered into a proposed Consent Decree and Environmental Settlement Agreement (“CDESA”) with the bankruptcy estate, the United States Environmental Protection Agency and various state environmental agencies to resolve certain environmental liabilities arising from various sites owned or operated by the debtor non-insurance affiliates. The CDESA was filed with the Court on April 3, 2026, and remains subject to Court’s approval.

Berkshire and certain of its subsidiaries are also involved in other kinds of legal actions, some of which assert or may assert claims or seek to impose fines and penalties. We currently believe that liabilities that may arise as a result of such other pending legal actions will not have a material effect on our consolidated financial condition or results of operations.

Commitments and other

On February 15, 2026, PacifiCorp and Portland General Electric Company and an affiliate of Portland General Electric Company (together, the “PGE Entities”) entered into an Asset Purchase and Service Area Transfer Agreement to sell to the PGE Entities certain PacifiCorp assets and liabilities associated with PacifiCorp’s Washington operations for a base sales price of $1.9 billion in cash. The transaction is subject to various regulatory approvals and customary closing conditions and is expected to close in the first half of 2027.