v3.25.4
Commitments and Contingencies (Estimated Planned Capital Expenditures) (Details)
$ in Millions
12 Months Ended
Dec. 31, 2025
USD ($)
MW
Planned Capital Expenditures [Line Items]  
Guarantor Obligations, Current Carrying Value $ 815
NEER Segment  
Planned Capital Expenditures [Line Items]  
2026 16,380
2027 10,730
2028 5,115
2029 1,650
2030 1,680
Total 35,555
Wind Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2026 2,750
2027 1,240
2028 1,050
2029 120
2030 110
Total $ 5,270
Planned New Generation To Be Added over 5 Years | MW 3,575
Solar Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2026 $ 8,045
2027 3,840
2028 1,620
2029 5
2030 10
Total $ 13,520
Planned New Generation To Be Added over 5 Years | MW 11,435
Other Clean Energy Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2026 $ 2,900
2027 3,070
2028 525
2029 15
2030 10
Total $ 6,520
Planned New Generation To Be Added over 5 Years | MW 4,616
Nuclear Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2026 $ 685
2027 1,070
2028 850
2029 525
2030 440
Total 3,570
Rate-Regulated Transmission [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2026 1,095
2027 1,050
2028 760
2029 650
2030 740
Total 4,295
Other Expenditures [Member] | NEER Segment  
Planned Capital Expenditures [Line Items]  
2026 905
2027 460
2028 310
2029 335
2030 370
Total 2,380
FPL  
Planned Capital Expenditures [Line Items]  
2026 11,185
2027 10,870
2028 11,605
2029 12,375
2030 12,595
Total 58,630
FPL | New Generation Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2026 4,255
2027 3,505
2028 4,365
2029 4,125
2030 3,525
Total 19,775
FPL | Existing Generation Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2026 1,180
2027 1,360
2028 1,300
2029 1,300
2030 1,350
Total 6,490
FPL | Transmission and Distribution Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2026 4,540
2027 4,910
2028 4,775
2029 5,900
2030 6,720
Total 26,845
Planned Generation Capital Expenditures AFUDC First Year 80
Planned Generation Capital Expenditures AFUDC Second Year 95
Planned Generation Capital Expenditures AFUDC Third Year 105
Planned Generation Capital Expenditures AFUDC Fourth Year 165
Planned Generation Capital Expenditures AFUDC Fifth Year 160
FPL | Nuclear Fuel Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2026 270
2027 340
2028 425
2029 385
2030 380
Total 1,800
FPL | General and Other Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
2026 940
2027 755
2028 740
2029 665
2030 620
Total 3,720
FPL | Generation Expenditures [Member]  
Planned Capital Expenditures [Line Items]  
Planned Generation Capital Expenditures AFUDC First Year 195
Planned Generation Capital Expenditures AFUDC Second Year 200
Planned Generation Capital Expenditures AFUDC Third Year 220
Planned Generation Capital Expenditures AFUDC Fourth Year 210
Planned Generation Capital Expenditures AFUDC Fifth Year $ 175