Contingencies and commitments (Details) $ in Millions |
2 Months Ended | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
|
Jan. 07, 2026
patent
|
May 15, 2025
USD ($)
|
Jan. 10, 2024
patent
|
Aug. 31, 2025
lawsuit
|
Dec. 31, 2025
USD ($)
installment
|
Sep. 30, 2025
state
|
Sep. 25, 2024
country
|
May 02, 2024
case
|
Apr. 11, 2024
case
|
Dec. 01, 2023
claim
|
|
| Other Commitments [Line Items] | ||||||||||
| Number of countries | country | 18 | |||||||||
| Alleged infringed patents | patent | 32 | |||||||||
| Number of litigation cases | case | 5 | |||||||||
| Damages awarded | $ 406.8 | |||||||||
| Number of states | state | 7 | |||||||||
| Number of lawsuits | lawsuit | 7 | |||||||||
| Loss contingency, number of additional claims | claim | 2 | |||||||||
| Number of securities cases | case | 2 | |||||||||
| U.S. repatriation tax commitments, number of annual installments | installment | 8 | |||||||||
| Final U.S. repatriation tax payment | $ 1,800.0 | |||||||||
| Subsequent Event | ||||||||||
| Other Commitments [Line Items] | ||||||||||
| Alleged infringed patents | patent | 19 | |||||||||
| Patents found not infringed | patent | 15 | |||||||||
| Compensatory Damages | ||||||||||
| Other Commitments [Line Items] | ||||||||||
| Damages awarded | 135.6 | |||||||||
| Punitive Damages | ||||||||||
| Other Commitments [Line Items] | ||||||||||
| Damages awarded | $ 271.2 |