REGULATORY MATTERS - GAS Schedule of Infrastructure Replacement Programs and Capital Projects (Details) - Southern Company Gas
$ in Millions
12 Months Ended
Dec. 31, 2024
USD ($)
mi
Dec. 31, 2023
USD ($)
Dec. 31, 2022
USD ($)
Public Utilities, General Disclosures [Line Items]      
Capital Expenditures in 2024 $ 186    
Capital Expenditures Since Project Inception $ 868    
Pipe Installed Since Project Inception (in miles) | mi 651    
Scope of Program (in miles) | mi 1,011    
SAVE      
Public Utilities, General Disclosures [Line Items]      
Capital Expenditures in 2024 $ 75    
Capital Expenditures Since Project Inception $ 561    
Pipe Installed Since Project Inception (in miles) | mi 598    
Scope of Program (in miles) | mi 938    
Program Duration 18 years    
System Reinforcement Rider      
Public Utilities, General Disclosures [Line Items]      
Capital Expenditures in 2024 $ 99 $ 104 $ 76
Capital Expenditures Since Project Inception $ 279    
Pipe Installed Since Project Inception (in miles) | mi 29    
Program Duration 6 years    
Pipeline Replacement Program      
Public Utilities, General Disclosures [Line Items]      
Capital Expenditures in 2024 $ 12    
Capital Expenditures Since Project Inception $ 28    
Pipe Installed Since Project Inception (in miles) | mi 24    
Scope of Program (in miles) | mi 73    
Program Duration 7 years