Accounting For Suspended Exploratory Well Costs
12 Months Ended
Dec. 31, 2011
Accounting For Suspended Exploratory Well Costs [Abstract]  
Accounting For Suspended Exploratory Well Costs

9. Accounting for Suspended Exploratory Well Costs

The Corporation continues capitalization of exploratory well costs beyond one year after the well is completed if (a) the well found a sufficient quantity of reserves to justify its completion as a producing well and (b) sufficient progress is being made in assessing the reserves and the economic and operating viability of the project.

The following two tables provide details of the changes in the balance of suspended exploratory well costs as well as an aging summary of those costs.

Change in capitalized suspended exploratory well costs:

 

     2011      2010      2009  
    (millions of dollars)  

Balance beginning at January 1

  $ 2,893       $ 2,005       $ 1,585   

Additions pending the determination of proved reserves

    310         1,103         624   

Charged to expense

    (213      (104      (51

Reclassifications to wells, facilities and equipment based on the determination of proved reserves

    (149      (136      (200

Other

    40         25         47   

Ending balance

  $ 2,881       $ 2,893       $ 2,005   

Ending balance attributed to equity companies included above

  $       $       $ 9   

Period end capitalized suspended exploratory well costs:

 

     2011        2010        2009  
    (millions of dollars)  

Capitalized for a period of one year or less

  $ 310         $ 1,103         $ 624   

Capitalized for a period of between one and five years

    1,922           1,294           924   

Capitalized for a period of between five and ten years

    409           278           220   

Capitalized for a period of greater than ten years

    240           218           237   

Capitalized for a period greater than one year – subtotal

  $ 2,571         $ 1,790         $ 1,381   

Total

  $ 2,881         $ 2,893         $ 2,005   

Exploration activity often involves drilling multiple wells, over a number of years, to fully evaluate a project. The table below provides a numerical breakdown of the number of projects with suspended exploratory well costs which had their first capitalized well drilled in the preceding 12 months and those that have had exploratory well costs capitalized for a period greater than 12 months.

 

     2011        2010        2009  

Number of projects with first capitalized well drilled in the preceding 12 months

             4                    9                 18   

Number of projects that have exploratory well costs capitalized for a period of greater than 12 months

           58                  59                 57   

Total

           62                  68                 75   

 

 

Of the 58 projects that have exploratory well costs capitalized for a period greater than 12 months as of December 31, 2011, 26 projects have drilling in the preceding 12 months or exploratory activity planned in the next two years, while the remaining 32 projects are those with completed exploratory activity progressing toward development. The table below provides additional detail for those 32 projects, which total $1,133 million.

 

Country/Project   Dec. 31,
2011
    Years
Wells Drilled
  Comment

                             (millions of dollars)

    

Angola

               

– Perpetua-Zina-Acacia

  $ 15      2008 - 2009   Oil field near Pazflor development, awaiting capacity in existing/planned infrastructure.

Australia

               

– East Pilchard

    10      2001   Gas field near Kipper/Tuna development, awaiting capacity in existing/planned infrastructure.

– SE Longtom

    15      2010   Gas field near Tuna development, awaiting capacity in existing/planned infrastructure.

Indonesia

               

– Natuna

    118      1981 - 1983   Development activity under way, while continuing discussions with the government on contract terms pursuant to executed Heads of Agreement.

Kazakhstan

               

– Kairan

    53      2004 - 2007   Declarations involving field commerciality filed with Kazakhstan government in 2008; progressing commercialization and field development studies.

Malaysia

               

– Besar

    18      1992 - 2010   Gas field off the east coast of Malaysia; progressing development plan.

– Other (2 projects)

    8      1979 - 1995   Projects primarily awaiting capacity in existing or planned infrastructure.

Nigeria

               

– Bolia

    15      2002 - 2006   Evaluating development plan, while continuing discussions with the government regarding regional hub strategy.

– Bosi

    79      2002 - 2006   Development activity under way, while continuing discussions with the government regarding development plan.

– Pegi

    32      2009   Awaiting capacity in existing/planned infrastructure

– Other (4 projects)

    13      2002   Pursuing development of several additional offshore satellite discoveries which will tie back to existing/planned production facilities.

Norway

               

– Gamma

    20      2008 - 2009   Evaluating development plan for tieback to existing production facilities.

– H-North

    15      2007   Discovery near existing facilities in Fram area; progressing development plans.

– Lavrans

    22      1995 - 1999   Development awaiting capacity in existing Kristin production facility; evaluating development concepts for phased ullage scenarios.

– Nyk High

    19      2008   Evaluating field development alternatives.

– Other (6 projects)

    26      1992 - 2010   Evaluating development plans, including potential for tieback to existing production facilities.

Papua New Guinea

               

– Juha

    28      2007   Working on development plans to tie into planned LNG facilities.

United Kingdom

               

– Fram

    55      2009   Progressing development and commercialization plans.

– Other (2 projects)

    14      2001 - 2004   Projects primarily awaiting capacity in existing or planned infrastructure.

United States

               

– Julia Unit

    78      2007 - 2008   Reached agreement with the Department of Interior and Department of Justice providing for suspension of production; progressing development plans with partners.

– Point Thomson

    449      1977 - 2010   Continuing discussions with government and partners on development plan.

– Tip Top

    31      2009   Evaluating development concept and requisite facility upgrades.

Total 2011 (32 projects)

  $